Project Lookahead – Schedule of Activity

As always, we are committed to informing you of potential impacts on our neighborhood. This page will be updated often, informing you of future construction activity.

Thursday, October 5, to Thursday, October 19, 2023

Estimations
  • The first shotcrete shoot for portions of the north and west perimeter walls will take place on 10/6/23.
  • Concrete will poured for the sump pit walls on 10/6/23.
  • Shotcrete at portions of the east and west perimeter walls is scheduled for 10/13/23.
  • Shotcrete at portions of the east and north perimeter walls is scheduled for 10/31/23.
 
 
Reminder: No parking signs are posted on Waldo Ave. from 7 a.m. to 5 p.m. on school days to allow for the safe ingress and egress of construction equipment.

Construction Lookahead Archive

List of 9 items.

  • September 21, to Thursday, October 5, 2023

     
    • Reinforcement of sump pit walls is scheduled to finish by 9/27/23.
    • Concrete columns will be formed by 10/6/23.
      Exterior garage shotcrete walls will be completed by 10/17/23.
  • August 10 to August 17, 2023

  • July 13 - July 20, 2023


    • Excavating dirt continuing to Aug 10, 2023
    • Interim modular classroom final fire alarm testing: Jul 13-14 and July 17-18, 2023
  • July 6 - July 13, 2023


    • Start of excavating dirt: Jul 7, 2023
      • continuing to Aug 10, 2023
    • Demobilization of drilling and vibrating equipment is complete.
    • Parking Complex drilling and vibrating beams are complete.
    • Interim modular classroom final fire alarm testing: Jul 14, 2023
  • July 7, 2023

    Free Neighbor Coffee & Donuts
    • Mayfield neighbors are invited to enjoy free coffee and donuts at the corner of Bellevue Dr. and Waldo Ave. on Friday, July 7, from 7:30-9:00 a.m.
  • June 29 - July 6, 2023


    • Start of pre-drilling and drilling beams and piles for shoring: June 26-July 5, 2023
    • Start of excavating dirt: Jul 7, 2023, continuing to Aug 10, 2023
    • Interim modular classroom final fire alarm testing: Jul 14, 2023
  • June 22 - 29, 2023

    • Fencing installation around trees on Bellevue Dr. and Waldo Ave.: June 21-22
    • Mobilizing large construction equipment and beams: June 21-23
    • Interim modular classroom fire alarm testing: Jun 26, 2023
    • Interim modular classroom final fire alarm testing: Jul 14, 2023
  • June 12-16, 2023

    Sound
    City of Pasadena Tree Trimming | June 12-16, 2023
  • June 14, 2023


    • Installation of piles at the field | Continuing to June 27, 2023
    • Dirt removal and transport on Waldo Ave. and Del Mar Blvd. | Continuing to August 8, 2023   
    • Interim modular classroom fire alarm testing | Jun 23, 2023
    • Interim modular classroom final fire alarm testing | Jul 14, 2023
May 2023

Hello Neighbor, 

Since 1931, Mayfield Junior School has challenged students to reach their potential by following the Holy Child philosophy of developing the Whole child as an intellectual, spiritual, creative, and athletic person. We strive to fully equip students, so they are best prepared for high and beyond, and to ultimately contribute to making our world a better place.

Head of School, Joe Sciuto, said it best, “A faculty of the highest quality, working with the most innovative teaching and learning resources available, this is how we best support and serve our students...”

Continuing to create effective teaching environments is critical to student learning. Mayfield, however, last completed a major campus improvement project more than 20 years ago with the development of the Lower School.

After three years of thoughtful planning including a series of community meetings, the City of Pasadena unanimously approved Mayfield’s Master Plan in February 2023 which includes a center for teaching and learning, an expanded underground parking area that adds nearly 90 new parking spaces reducing neighborhood impact, and an improved, environmentally friendly outdoor playing field.

Special Event Dates 2023-2024

 
The following events are approved to be outside of normal business hours and host 100 + people (Normal business hours are M-F 8:00-5:00 pm). CUP allows for 18 events.
 

September 10: Opening Mass
(9:00 am)

September 14: Lower School Back To School Night (5:00 pm)

September 21: Middle School Back To School Night (5:00 pm)

September 28: 8th Grade BTSN & HS information night (5:00 pm)

October 3: HS Options Fair (7:00 pm)

November 3: Family Softball/BBQ (3:30 pm - 10:30 pm in the Gym)

November 14: 2nd-grade Sacramental Program, Meet the Priest (5:00 pm)

January 20: Kindergarten playdate (8:00 am - 1:30 pm)

April 20: First Eucharist (10:00 am)

April 26: 8th Grade Play (7:00 pm)

April 27: 8th grade play (7:00 pm)

April 28: 8th grade play (2:00 pm)

May 30: Grad Night (6:00 pm - 10:00 pm)

June 5: Baccalaureate (5:00 pm)

June 6: Graduation (5:00 pm)

MJS Branch Fall 2023

Notice


Please note this update from the City of Pasadena. As a clarification, this work is not connected to a Mayfield Junior School project.